Oct 2026
Frame at floor 9
Floors 8 and 9 poured this month. Scaffolding moves up next week.
04Trust
Dates we promised, dates it happened, photos every month. If something slips, you read it here first.
Keys
Q2 2028
unchanged since launch
Now
Floor 9 / 14
frame in progress
Stages on time
2 of 3
one 3 weeks late - see why
The quarry moved our travertine panel delivery by a month, so the frame crew re-sequenced the floors. The keys date does not change.
📷Construction log

Oct 2026
Floors 8 and 9 poured this month. Scaffolding moves up next week.

Jun 2026
Two floors a month since spring. Lift shafts are ahead of the slabs.

Jan 2026
The arcade columns are cured; the crane is extended for the tower.

Oct 2025
Foundations done two weeks early. Arch moulds are on site.
â—ŽDeveloper
141 homes delivered since 2009. Here is every building - including the late one.

2019 · 42 homes
Keys on the promised date
2021 · 5 homes
Keys on the promised date
2022 · 58 homes
Keys 2 months lateA bankrupt glazing subcontractor. Every buyer received the late-delivery payment from the contract.

2024 · 36 homes
Keys 3 weeks early