0 Talk to us

04Trust

Promised.
Actual.

Dates we promised, dates it happened, photos every month. If something slips, you read it here first.

Keys

Q2 2028

unchanged since launch

Now

Floor 9 / 14

frame in progress

Stages on time

2 of 3

one 3 weeks late - see why

StagePromisedActual
Permit and groundworkMar 2025Mar 2025On time
Foundations and arcadeOct 2025Sep 20252 weeks early
Frame to floor 9Sep 2026Oct 2026+3 weeks

The quarry moved our travertine panel delivery by a month, so the frame crew re-sequenced the floors. The keys date does not change.

Frame to floor 14Jan 2027Jan 2027In progress
Facade closedAug 2027-Planned
Interiors and liftsJan 2028-Planned
KeysQ2 2028Q2 2028Unchanged

📷Construction log

Same camera, every month.

Frame at floor 9

Oct 2026

Frame at floor 9

Floors 8 and 9 poured this month. Scaffolding moves up next week.

Floors 5-7

Jun 2026

Floors 5-7

Two floors a month since spring. Lift shafts are ahead of the slabs.

First floor slab

Jan 2026

First floor slab

The arcade columns are cured; the crane is extended for the tower.

Arcade formwork

Oct 2025

Arcade formwork

Foundations done two weeks early. Arch moulds are on site.

â—ŽDeveloper

Tilleul Development.
Our record.

141 homes delivered since 2009. Here is every building - including the late one.

Rue Basse 12

Rue Basse 12

2019 · 42 homes

Keys on the promised date
Les Cèdres townhouses

Les Cèdres townhouses

2021 · 5 homes

Keys on the promised date
Harbour 8

Harbour 8

2022 · 58 homes

Keys 2 months late

A bankrupt glazing subcontractor. Every buyer received the late-delivery payment from the contract.

Parc Terraces

Parc Terraces

2024 · 36 homes

Keys 3 weeks early